Delivery track record · Dubai · July 2026

Which developers deliver on time, ranked by the closest proxy the data supports

"Which developers deliver on time" has no true answer in this corpus. An on-time rate needs two dates for the same building, an originally announced handover and the actual one, and the corpus holds only the date each listing states today. So this is a proxy, not a rate, and it is labelled that way everywhere it appears: the share of a developer's own off-plan projects whose own stated handover date has already passed while the source still records the project as under construction. A high share does not prove delay. A listing nobody refreshed looks identical to a genuinely late building, so read this as a flag to check against the developer's own site, not a finding on its own.

58 developers carry n/a or more dated off-plan projects and clear the floor to publish a share. Aldar has the lowest on record at 0%, against a market share of 6% across 2,858 dated off-plan projects. AYS carries the highest at 25%. Completions on record sit alongside the proxy in the table, because a developer with a long, dated delivery history is easier to read than one with none.

Developers ranked
58
at n/a+ dated off-plan projects
Market past-handover share
6%
169 of 2,858 dated off-plan projects
Lowest share on record
0%
Aldar
Completions on record, market
1,083
96% since 2020
58 developers with n/a or more dated off-plan projects, fewest overdue first

Past-handover share, ascending

#DeveloperPast its own handover dateShare overdue (proxy)Completions on recordSince 2024First to last completion
1Aldar0 of 1320%26252023 to 2026
2Alef0 of 390%772024 to 2025
3Avenew0 of 130%00n/a
4Beyond0 of 220%202020 to 2023
5Bloom Holding0 of 170%1062019 to 2026
6BT0 of 100%00n/a
7Burtville0 of 140%00n/a
8Dubai South Properties0 of 160%992024 to 2026
9Dugasta0 of 90%512019 to 2025
10Durar0 of 90%322021 to 2025
11Emirates0 of 100%222025
12GFS0 of 150%00n/a
13Majid Al Futtaim0 of 150%642023 to 2026
14Majid Al Futtaim (MAF)0 of 80%222024 to 2026
15Mira Developments0 of 100%00n/a
16Modon0 of 250%00n/a
17Mr Eight0 of 80%00n/a
18Omniyat0 of 170%412017 to 2025
19Reef Luxury0 of 90%00n/a
20Select Group0 of 100%15122018 to 2026
21Seven Mayfair0 of 100%00n/a
22Taraf0 of 140%212023 to 2025
23Union P.J.S.C0 of 80%112024
24Wasl0 of 190%432023 to 2025
25Zaya0 of 120%112025
26Zoya0 of 120%00n/a
27Emaar2 of 2291%92492019 to 2026
28Nakheel1 of 841%15102017 to 2026
29DAMAC3 of 1692%74472013 to 2026
30Sobha Realty2 of 972%12102023 to 2026
31Azizi2 of 603%74362017 to 2026
32H&H1 of 264%432023 to 2026
33Eagle Hills1 of 215%16112022 to 2026
34RAK1 of 215%16142023 to 2026
35Reportage2 of 385%12102022 to 2026
36Nshama2 of 307%13112021 to 2026
37Object 14 of 587%332024 to 2026
38BNW1 of 147%00n/a
39Prestige One1 of 147%322023 to 2025
40Arada4 of 508%38302022 to 2026
41Expo City Dubai1 of 128%662025 to 2026
42Meraas5 of 549%41352021 to 2026
43Imtiaz4 of 4110%652023 to 2025
44AG1 of 911%102020
45Rabdan1 of 911%00n/a
46Samana6 of 5112%542023 to 2026
47HRE1 of 813%00n/a
48Tiger Properties3 of 2313%742023 to 2025
49Ellington9 of 6614%21182019 to 2026
50Danube3 of 2114%972023 to 2026
51Deyaar2 of 1414%1252011 to 2025
52Iman Developers2 of 1217%542023 to 2025
53Binghatti10 of 5518%31202020 to 2026
54LEOS International2 of 1118%222025
55MAG2 of 1118%14102023 to 2026
56GJ3 of 1619%632019 to 2024
57Peace Homes2 of 922%112024
58AYS2 of 825%102022

"Past its own handover date" counts off-plan projects whose published handover quarter has already passed while the project is still recorded as under construction, one observation per project. Ranked ascending, fewest overdue first, so the top of the table is the strongest signal, not the largest number. Completions, "since" and "first to last" are the same completions-on-record measure the developer scorecard uses, over delivered buildings, not off-plan ones.

Definitions and thresholds

How this is computed

Computed in pipeline/developer_scorecard.py from the past_handover measure: n_dated_offplan is off-plan projects with a parsed handover date, n_past is how many of those dates fall before July 2026, and share_pct is n_past over n_dated_offplan. Published only at n/a+ dated projects, the same evidence floor the developer scorecard applies to this measure. See /rankings/developer-scorecard for completions, price position, plan depth, footprint and completeness measured the same way, with the same refusal to publish a composite grade. Figures are OffplanIndex aggregates over developer-published project facts and unit inventories, not a copy of any listing database.

Full definitions, exclusion rules and sources are in the methodology, and what we do and do not republish is set out in the data policy. Built 2026-10-02 from data observed to 2026-07-30. Not investment advice.

Same data, different question

Related rankings

Or start from a place: every community and every developer has its own benchmark page, and all rankings are listed together.

Dubai Off-Plan Q3 2026

The full report: every community, every developer, ranked.

Delivery track record in context: price per sqft by community and developer, payment plan structures ranked by cash due before handover, the 2026 to 2029 delivery pipeline, and the CSV behind every table. PDF plus data, delivered instantly.